Many project managers have been
taught to estimate the effort that a task requires instead of
estimating the duration as is promoted by the views in Microsoft
Project. As you recall work (which is the name used for effort in
Project), along with duration and units are the
components of the work equation that Project applies to resource assignments:
Duration * Units = Work
If the manager has estimated work
and has decided not only which resources to assign but also how many units of
each will be assigned, then Project can calculate the duration using this
version of the formula:
Duration = Work / Units
In this article we will look at how
you record the task's total work (leaving the duration at the default "1
day?" for the time being) and then how you create the resource assignments
to achieve your objective.
The task Work field records total
work for a task. Normally, its value is calculated by Project as the rolled-up
sum of work assigned to all resources for the task. But, you can enter the value
yourself for Project to distribute among assigned resources. You can add the
Work field to any task table. It's already displayed in the Usage table; so
we'll just use that table.
If you like working with the Gantt
Chart then you can apply the Usage table to that view (instead of the Entry
table which is the default). Right-click over the Select All button (the
unmarked header above the ID column) and choose Usage.
In the Usage table the Work column
is displayed between the Task Name and Duration columns. This table also has the
Start and Finish columns, but it does not by default have the Predecessors and
Resource Names columns. Top
Note: once you apply the Usage
table to the view it will remain the table displayed by that view (at least in
the project file you are working in). To return to the standard Gantt Chart
view, right-click the Select All button again and choose Entry.
Alternatively, you can simply
display the Task Usage view which uses the Usage table by default. It also
replaces the Gantt task bars with a grid of timephased data.
You can enter all the task names in
this view, just as easily as you can in the Gantt Chart: indenting tasks to
create the outline, linking tasks to show their dependency relationships,
double-clicking a task name to display the Task Information dialog in order to
define other aspects like deadline dates, constraint dates, and so forth. You
can also split the window to display the Task Form for creating the resource
assignments and further defining the task.
Whichever view you use, display the
Usage table and create your task list, entering Work but leaving Duration with
the default "1 day?". Project will later calculate the duration when
you assign the resources.
Of course if you have a fixed
duration task, enter the duration and change the task type to Fixed Duration. If
you also have the work for this task, you will have to let Project calculate the
units instead of the duration. Top
Once you have recorded work for the
tasks, you can assign the resources. Since you have defined the total work for
the task, then if you plan to assign multiple resources to a task you must make
sure that it is Effort Driven.
You don't have to remain in the
Usage table, but it's probably wise to stay there for the time being. You might
get carried away experimenting with assignments and accidentally change the work
value for a task.
Note: this discussion does not
cover Fixed Duration tasks - only Fixed Units and Fixed Work. Since we are
defining the total work associated with tasks, we also assume the tasks are
Effort Driven (but they don't have to be Fixed Work).
You can use the Assign Resources
dialog box or the Task Form to assign the resources. As you know, I usually
recommend the Task Form because you have greater control over the work equation
calculations.
If you're assigning just a single
resource to the task, it's very simple. Simply select the task in the top pane,
enter the resource name in the Task Form AND enter the units before
clicking OK. Note that you must enter the units, even if you want to use the
default 100%. If you don't enter the units, since duration and work
already have values Project will keep those values (with duration at 1 day) and
calculate enough units to do all the work in 1 day.
If you're assigning multiple
resources, and if you want Project to distribute the work evenly among
them, then it's just as simple as assigning one resource. Just list all the
resources and fill in the units before clicking OK. Project will distribute the
work evenly among them.
Note, however, that Project will
distribute the total work evenly among them even if they don't all have
the same units assignment. Those with more units will be able to finish their
work more quickly than those with fewer units.
But, if you're assigning multiple
resources with different units and you want Project to distribute the work in
proportion to their units, then it's slightly more involved.
For example, suppose you create a
task named Design Data Model in a large IT project and estimate it will
take 900 hours of work to complete. If you were to assign a single senior
programmer named Tony to the task, you could enter the work when you assign
Tony, along with the units (for instance 100% ) and Project would calculate the
duration for you (assuming the task is not Fixed Duration). However if there's
that much work involved you might want to assign other programmers to the task
because it will take Tony about half a year to finish.
Suppose that instead of using only
Tony you plan to assign three resources:
You want all three programmers to
work for the full duration of the task; but you're assigning Tony to spend only
half of his time on this task and you want his work hours to be half the amount
that is assigned to each of the other two programmers.
To get Project to distribute the work like we want you need to assign just one of the resources first. For instance if you assign Tony at 50% Project will assign all 900 hours of work to him and calculate duration of 225 days. Then you can assign the other programmers, specifying units of 100%, and because the task is Effort Driven Project will redistribute the work among them in proportion to their units contribution (see Table 1). All three resources work for 45 days on the task, with Tony spending only half of each day on this particular task.
Table
1
|
|
Units
|
Work
|
Duration |
|
Tony |
50%
|
180
hours |
(45
days) |
|
Programmer 1 |
100%
|
360
hours |
(45
days) |
|
Programmer 2 |
100%
|
360
hours |
(45
days) |
|
Task Total |
|
900
hours
|
45
days |
Effort Driven calculations only kick in when you change the number of resource
names assigned to a task after the initial assignment. For instance, if you were
to change Tony's assignment to 100% Project would not redistribute the work
among the resources - it would just change Tony's schedule. Table 2 shows
the what project would do if you increase Tony's units from 50% to 100%.
Project just schedules his hours over a shorter time period.
Table
2
|
|
Units
|
Work
|
Duration |
|
Tony |
100%
|
180
hours |
(22.5
days) |
|
Programmer 1 |
100%
|
360
hours |
(45
days) |
|
Programmer 2 |
100%
|
360
hours |
(45
days) |
|
Task Total |
|
900
hours |
45
days |
So, what can you do to make Project redistribute the work evenly if we make
Tony's units the same as the others? As pointed out above, the Effort Driven
calculations only work when you add or delete named resources. You would need to
delete Tony as a resource, click OK, and then add him back with 100% units.
Conclusion
Traditional project management training often teaches managers to estimate
effort (work) for tasks and to decide what resources will be assigned. The
presumption is that the software will calculate the duration and distribute the
work in proportion to the assigned units. You can do that in Project, but you
need to use this method:
|
|
[Home] [About
Us] [Services] [Events] [Register] [search] [Contact
us] [Members] [Web
board] |