Performance Measurement Data
Analysis
A
Performance Measurement System provides data and reports required for effective
analysis of variances. Performance Measurement variances result from comparison
of Scheduled Work (SW), Performed (P), Actuals (A), Budget at Completion (BAC)
and Estimate at Completion (EAC).
Comparison
of Scheduled Work (SW) and Performed (P) provide an indication of aggregate
schedule performance. The comparison, however, may not clearly represent the
performance of work associated with specific milestones. Some work may have been
accomplished out of sequence or ahead of schedule. Therefore, the formal
time-phased scheduling system needs to be used to determine the status of
specific activities and milestones.
Comparison
of Performed (P) and Actuals (A) clearly indicates whether the work completed
has cost more or less than was planned for that work. Analysis of these
variances should reveal the factors which are causing the deviation from plan.
Comparison
of BAC and EAC provides an estimated variance at the completion, of the planned
element of work.
At
the Task Manager level, the Task Managers analyzes variances which result from
comparison of these five basic data elements, SW, P, A, BAC and EAC. Summarized
data is used to provide contract status at the various levels of the Contract
Work Breakdown Structure (CWBS) and organizational (OBS) performance data at all
levels of management. This is why the Responsibility Assignment Matrix (RAM) is
such an important tool. Back to Top
Types of Variances
The
data available from the Performance Management System (SW, P, A, BAC, EAC,
Schedule Variance (SV), Cost Variance (CV) and Variance at Completion (VAC))
provides the current period and the cumulative to date performance status
information for each CWBS and OBS element and level. If a significant variance
is identified, then this data provides an indication of the magnitude of the
potential contract impact in the future. Cost variances, schedule variances, and
at completion variances are reviewed and reported at the Task Plan level to:
|
Variances will always exist, unless there is
perfect execution of the Project Plan. Variances are not always a bad
omen, or cause of concern, or an indicator of poor management.
Significant variances are those variances that break predetermined
thresholds, require management attention, and corrective action.
Significant variance may mean the original plan was inappropriate, or
the EVT was not appropriate, or the actuals (ACWP) were incorrect.
Significant variances inform management that something needs to be
examined, analyzed and proper corrective action instituted. |
Schedule
Variance (SV)
Comparing
the value of work performed with the value of work scheduled determines Schedule
Variance (SV). SV is a subjective indicator. It does not reveal the critical
path. SV is an aggregate dollarized value of events ahead or behind schedule.
Arithmetically, SV is expressed as:
|
Commercial
ProjectsSV = P - SW |
Government
ProjectsSV = BCWP - BCWS |
A
positive schedule variance is an indication that in-process work is ahead of
schedule. A negative schedule variance indicates that the in-process work is
behind schedule.
Cost
Variance (CV)
Comparing
the value of work performed with the actual cost of work performed determines
Cost Variance (CV). CV is an objective indicator. CV is a dollarized value of
what was accomplished for the resources expended. Arithmetically, this is
expressed as:
|
Commercial
ProjectsCV = P - A |
Government
ProjectsCV = BCWP - ACWP |
A
positive cost variance indicates that work was accomplished for less resource
expenditure than planned. A negative cost variance indicates that work
accomplished cost more than planned resource value.
Variance
At Completion (VAC)
Comparing
the Budget at Completion (BAC) with the latest Estimate of Completion (EAC)
determines the Variance at Completion (VAC). The VAC formula is arithmetically
expressed as:
|
Commercial
ProjectsVAC = BAC – EAC |
Government
ProjectsVAC = BAC - EAC |
Performance
indices show the percentage of variation, between planned and actual
performance, for the current period, cumulative to data time span, and at the
completion of the task.
The
Schedule Performance Index (SPI) and Cost Performance Index (CPI) are calculated
in order to provide an efficiency factor for work accomplished during the
current period and for cumulative data. The To-Complete-Performance-Index (TCPI)
calculates an efficiency factor which must be attained, if the remaining work
scope in order to complete the Cost Account within the forecasted EAC. The
following paragraph discusses the analysis techniques that produce these
performance indices.
Examples
of SPI, CPI and TCPI are calculated using the following cumulative-to-date data:
|
Scheduled$45,600 |
Performed$50,800 |
Actual$42,900 |
BAC$200,000 |
EAC$180,000 |
Schedule Performance Index (SPI)
The
ratio of work accomplished versus work planned, for a specified period of time,
defines the SPI. The SPI is an efficiency rating for work accomplishment. The
SPI compares work accomplished to what should have been accomplished.
|
Commercial
ProjectsSPI = P/SW |
Government
ProjectsSPI = BCWP/BCWS |
ExampleSPI
= 50,800/45,600 |
SPI1.11% |
This
formula produces a SPI which is referred to as SPIe. The e is an efficiency
designation. The inverse of the formula, SW/P = SPIp. The p is a performance
designation. The analyst should designate which SPI is being used in the
Schedule Variance discussion.
The calculated SPI indicates that 1.11% of the work scheduled to be completed, has been completed through the current period. An favorable or ahead schedule indication exists. The analyst needs to keep in mind and be aware that a SPI of 100% indicates an on schedule condition. However, this performance indication may not necessarily provide the true status of the work accomplished, since some work may have been performed out of sequence or ahead of schedule. The Task Plan and program schedules must be used in conjunction with the SPI to provide valid Work In Process (WIP) status information.
Cost
Performance Index (CPI)
The
CPI is defined as the ratio work accomplished versus work cost incurred for a
specified period of time. The CPI is an efficiency rating for work accomplished
for resources expended.
|
Commercial
ProjectsCPI = P/A |
Government
ProjectsCPI = BCWP/ACWP |
ExampleCPI
= 50,800/42,900 |
CPI1.18% |
This
formula produces a CPI which is referred to as CPIe. The e is an efficiency
designation. The inverse of the formula, A/P = CPIp. The p is a performance
designation. The analysis required to designate which CPI is being used in the
Cost Variance discussion.
The calculated CPI indicates that for each actual $1.00 of resource expended $1.18 in earned value was received. A cost underrun or higher than planned efficiency indication exists for the period analyzed.
Schedule
Variance Percent (SV%)
To
arrive at a meaningful indication of schedule performance, the Schedule Variance
(SV) must be related to the amount of work planned to have been accomplished.
This is accomplished by converting the SV stated in dollars into a Schedule
Variance Percent (SV%).
|
Commercial
ProjectsSV(%) = P - SW / SW |
Government
ProjectsSV(%) = BCWP-BCWS / BCWS |
ExampleSV(%) = 50,800 - 45,600 / 45,600 |
SV(%)+.114 |
The
example indicates that the Task Plan is 11.4% ahead of schedule. This cumulative
calculated index data provides results consistent with the cumulative calculated
SPI.
Cost
Variance Percent (CV%)
To
arrive at a meaningful indication of cost performance the Cost Variance (CV)
must be related to the amount of work accomplished. This can be accomplished by
converting the CV stated in dollars into a CV stated as a percentage.
|
Commercial
ProjectsCV(%) = P - A / P |
Government
ProjectsCV(%) = BCWP-ACWP / BCWP |
ExampleCV(%)
= 50,800 - 42,900 / 50,800 |
CV(%)+.155 |
The
example indicates that the Cost Account is 15.5% under target cost. The
cumulative CV calculated index data provides results consistent with the
previous cumulative calculated CPI.
Percent
Complete/Percent Spent
The
percent complete is the budget percent complete. Sometimes the Project Manager
or PMO use time percent complete. Time percent complete is based on duration or
time spans from a Network Logic Schedule (NLS) and normally does not equal
budget percent complete. The criteria for a Performance Measurement system uses
budget percent complete - - - not time percent complete. The Project Management
Office (PMO) should perform analysis using all available data in the management
information system.
Percent
complete is the relationship of the amount of work performed to date (P) to the
amount of work scheduled (SW) for a specific element of the CWBS or the OBS. The
base used to determine percent complete is the Budget at Completion (BAC).
The
percent of work complete should then be analyzed by comparing it to the percent
of work planned or scheduled to have been accomplished through the reporting
period being analyzed.
By
comparing the value of the work completed (25%) to the value of the work
schedule for completion (23%) the conclusion of this comparison should yield
results compatible with the calculated SV% (+10.2). The results in this example
indicate that the effort is 2% (25% - 23%) ahead schedule at this time.
The
percent spent can be calculated using two different approaches;
(1)
comparison
of Actuals with BAC and
(2)
comparison
of Actuals with EAC.
Analysis
to determine realization of the EAC is performed by comparing the percent
complete to percent spent. By using the data from the example provides an
indication that the current EAC (180,000) may be understated and mathematically
may be closer to $192,000 (25% of the work has been accomplished utilizing 21%
of the budget instead of 24% of the budget as indicated by the EAC). This
indicator points to the need for further review, of the remaining work scope
value. This will help to determine the accuracy of the projected EAC.
To
Complete Performance Index (TCPI)
The
analysis techniques discussed above are used for activities which have already
taken place. The analysis data is based on past performance and the results
cannot be changed; however, the footprints left by these activities and events
can be used to project future performance trends.
The
To Complete Performance Index (TCPI), also known as the verification factor, is
defined as the ratio of remaining work to remaining budget. The TCPI is
calculated using cumulative-to-date information only.
|
TCPI
DefinitionPlanned value of the work remaining / The estimated cost to
complete |
TCPI
FormulaTCPI = BAC - P / EAC - A |
ExampleTCPI
= 200,000 - 50,800 / 180,000 - 42,900 |
TCPI(%)109% |
The
TCPI when compared to the cumulative-to-date CPI provides a meaningful data
analysis tools which can be used to determine the accuracy of the remaining or -
to complete - effort. A difference between the TCPI and cumulative-to-date CPI
of more than ± 20% indicates that the EAC will probably not relate to the past
performance. Using the cumulative-to-date CPI and TCPI calculations from the
example:
Cumulative-to-date
CPI = 118% and TCPI = 109%
The
TCPI indicates that the Task Manager is projecting the performance on the
remaining work will be accomplished at a decreased efficiency. For each budget
dollar spent to date, $1.18 in value was received. Based on the TCPI of 109%,
for each budget dollar of work remaining, $1.09 in value will be achieved. The
efficiency factor for the remaining work scope is forecasted to decrease by 9%.
terms
“Earned
Value", Management by Objectives", and "Performance
Management" are interchangeable.
"Cost Account Manager"(CAM), "Cost Account Leader"(CAL), and
"Task Manager" (TM) are interchangeable.
"Cost Account Plan"(CAP), ", and "Task Plan" (TP) are
interchangeable.
"Budgeted Cost of Work Scheduled" (BCWS) and "Scheduled
Work" (SW) are interchangeable.
"Budgeted Cost of Work Preformed" (BCWP) and "Performed" (P)
are interchangeable.
"Actual Cost of Work Preformed" (ACWP) and "Actuals" (A) are
interchangeable.
"Project" as in Project Master Schedule and " Program" as in
Program Master Schedule are interchangeable.
|
|
[Home] [About
Us] [Services] [Events] [Register] [search] [Contact
us] [Members] [Web
board] |