Editing Actual Work In MS Project
One of Project's strengths is
its ability to adjust variables as a project changes. For example, if you change
the Actual Work hours on a project, the application will adjust the duration
over the appropriate time period. Let's look at an example of a project with a
two-day duration and a Fixed Units task.
If we assign a resource to
this task at 100 percent units, the resource by default is assigned to work two
eight-hour days, making the task a 16-hour effort. If you mark this task as 50
percent complete and then look at the Task Usage view (right-click in the
Timescaled area and then select Actual Work from the menu), you'll see that the
task is broken down into two eight-hour days with eight hours of Actual Work for
the first day.
What
do you think will happen if you change the eight hours of Actual Work for that
first day to six hours? How will the task change? Because it is a Fixed Units
task, Project will take those two hours and add them on the task onto a
third day, making the task a 2.25-day duration task.
What
about if we had made that same edit to a task that was a Fixed Duration
task type? The hours have to go somewhere, but the task type suggests that it
should not be to the third day. Therefore, Project adds them onto the end of the
second day, making the second day a 10-hour day for our resource. This bumps the
Assignment Units value to 125 percent.
What
if the task was Fixed Work? We're changing work values for a Fixed Work
task, so what happens? Anytime work is edited on a Fixed Work task, Project will
edit the duration. So in this case, the two hours are added to the third day,
just as in the Fixed Units case.
|
|
[Home] [About Us] [Services] [Events] [Register] [search] [Contact us] [Members] [Web board |