Clear
a Baseline Plan
Microsoft
Project now includes the option to clear a baseline or interim plan on a
project.
1.
To clear baseline information for specific tasks only, select those
tasks. To clear baseline information for the entire project, start with step 2.
2.
Point to Tracking on the Tools menu, and then click Clear
Baseline.
3.
Click Clear baseline plan or Clear interim plan. To clear
an interim plan, you need to select it in the list box.
4.
Click Entire project or Selected tasks.
|
|